| Number of credits available | Minimum standards |
|---|---|
| 2 | No |
To encourage the use of previously occupied and/or contaminated land and avoid land which has not been previously disturbed.
This issue is split into two parts:
The following is required to demonstrate compliance:
None.
| Ref |
Terms |
Description |
|---|---|---|
| Shell and core | ||
|
CN1 |
Applicable assessment criteria |
Both options: All criteria relevant to the building type and function apply. Refer to Appendix D – BREEAM UK New Construction and Shell and Core Project Assessments for a more detailed description of the above shell and core assessment options. |
| Simple buildings | ||
|
CN2 |
Applicable assessment criteria | All criteria relevant to the building type and function apply. |
| General | ||
|
CN3 |
Temporary works See criterion 1. |
Undeveloped areas of the site to be used for temporary works (e.g. temporary offices/parking, material/machinery storage) must be considered as development on undeveloped land and therefore included in the calculations unless they have been defined as ‘land of low ecological value’ (LE 02 Ecological value of site and protection of ecological features). |
|
CN3.1 |
Infill development See criterion 1. | New buildings developed within the boundary of existing sites do not automatically comply with the reuse of land criteria. At least 75% of the land on which the new building will be sited must meet the definition of 'previously occupied' (for prisons, refer to the building type specific compliance note below). |
|
CN3.2 |
Prior decontamination See criteria 2 and 3. |
The credit for use of contaminated land can only be awarded where remediation has taken place to enable development of the site for the assessed building, or a larger phased development that includes the assessed building (see below). The credit is not achievable for instances where historical remediation and development of the site has occurred outside the scope of the current development proposals. |
|
CN3.3 |
Large sites split into smaller plots See criteria 2 and 3. |
Where contamination of a large site has been remediated and has then been packaged up into smaller plots of land for individual buildings (possibly as part of a phased development strategy), the credit can be awarded regardless of the plot location of the assessed building within the wider development plan. This is on the condition that the site could not have been developed without remediation work taking place. |
|
CN3.4 |
Health and safety related decontamination See criteria 2 and 3. |
Contaminated land that has been decontaminated solely for health and safety reasons (rather than for the specific purpose of re-development) does not comply. |
|
CN3.5 |
Asbestos See criteria 2 and 3. |
Where the only remediation required is the removal of asbestos within an existing building fabric, the site cannot be classified as contaminated land. However, where asbestos is found to be present in the ground this will be classed as contamination for the purposes of assessing this issue. |
| Building specific | ||
|
CN4 |
Education (schools only) Playing fields See criterion 1. |
Development of a playing field within the construction zone can be counted as development on previously occupied land only if an equivalent area of playing field is reinstated within one year of the completed construction works; and where such reinstatement will not encroach on land of high ecological value as defined in BREEAM issue LE 02 Ecological value of site and protection of ecological features |
|
CN4.1 |
Prisons See criterion 1. |
All land within a secure perimeter fence on an existing prison sites can be classified as previously occupied land. Therefore assessments of buildings located within this area will achieve the credit. If the secure perimeter fence of a prison is being extended to accommodate the proposed building, or the proposed building is located on a completely new site, then the building must comply with the assessment criteria defined above. |
None.
| Criteria | Interim design stage |
Final post construction stage
|
|---|---|---|
| All |
One or more of the appropriate evidence types listed in The BREEAM evidential requirements section can be used to demonstrate compliance with these criteria. |
|
| 3 | A copy of the remediation strategy and implementation plan | As per interim design stage |
None.
BREEAM UK New Construction non-domestic buildings technical manual 2014
Reference: SD5076 – Issue: 5.0
Date: 23/08/2016
Copyright © 2016 BRE Global. All rights reserved.