Number of credits available | Minimum standards |
---|---|
1 | No |
To recognise and encourage the use of thermal insulation which has a low embodied environmental impact relative to its thermal properties.
The following is required to demonstrate compliance:
None.
Ref |
Terms |
Description |
---|---|---|
Shell and core | ||
CN1 |
Applicable assessment criteria |
Embodied impact - criteria 1 to 2 Both options: All new insulating products being specified or installed by the developer must be accounted for in the assessment of this issue. Refer to Appendix D – BREEAM UK New Construction and Shell and Core Project Assessments for a more detailed description of the above shell and core assessment options. |
Simple buildings | ||
CN2 |
Applicable assessment criteria | All criteria relevant to building type and function apply. |
General | ||
CN3 |
Insulation incorporated as part of an off-site manufactured element | If the insulation is incorporated as a component of an element that has been manufactured off-site (in order to maximise material optimisation), e.g. a wall or roof, and that element has been assessed as part of Mat 01, then for the purpose of assessing the insulation for this BREEAM issue, a Green Guide rating of A+ should be used. The same rule applies to insulation that has a significant additional function, such as providing supporting structure, e.g. structural insulated panels (SIPS). In the Green Guide, the actual insulation will be listed within the element title, rather than under the generic insulation category. |
The Insulation Index is calculated using the BREEAM Mat 04 calculator which uses the following calculation methodology:
For each type of thermal insulation used in the relevant building elements, the volume weighted thermal resistance provided by each type of insulation is calculated as follows:
The volume weighted thermal resistance for each insulation material is then multiplied by the relevant Green Guide point(s) from the following table to give the Green Guide rating corrected value:
Table 49 Green Guide rating points/element
Green Guide rating | Points/element |
---|---|
A+ | 3 |
A | 2 |
B | 1 |
C | 0.5 |
D | 0.25 |
E | 0 |
To calculate the Insulation Index, the sum of the Green Guide rating corrected values for all insulating elements is divided by the sum of the volume weighted thermal resistance values. See example calculation below.
Note
The Insulation Index is calculated for a building using the following types of insulation:
Type 1 Walls
Area = 450m²
Thermal insulation thickness = 100mm
Thermal conductivity = 0.023W/mK
Green Guide rating = A (2 points)
Volume weighted thermal resistance: ((450 x 0.100)/ 0.023) = 1956
Green Guide rating correction: 1956 x 2 = 3912
Type 2 Building services
Volume of insulation used = 21m³
Thermal conductivity = 0.022W/mK
Green Guide rating = C (0.5 points)
Volume weighted thermal resistance: (21/0.022) = 955
Green Guide rating correction: 955 x 0.5 = 477
Type 3 Roof
Area = 210m²
Thermal insulation thickness = 120mm
Thermal conductivity = 0.027W/mK
Green Guide rating = A+ (3 points)
Volume weighted thermal resistance: ((210 x 0.120)/ 0.027) = 933
Green Guide rating correction: 933 x 3 = 2799
Type 4 Ground floor
Area = 210m²
Thermal insulation thickness = 120mm
Thermal conductivity = 0.027W/mK
Green Guide rating = B (1 point)
Volume weighted thermal resistance: ((210 x 0.120)/ 0.027) = 933
Green Guide rating correction: 933 x 1 = 933
Total volume weighted thermal resistance = 1956 + 955 + 933 + 933 = 4777
Green Guide rating correction = 3912 + 477 + 2799 + 933 = 8121
Insulation Index: Green Guide Rating Correction/Total volume weighted thermal resistance = 8121/ 4777 = 1.7 (credit not achieved)
Please refer to Mat 01 Life cycle impacts – Methodology
Note: Step 1 of the methodology outlined in BREEAM issue Mat 01 (the proportion of the total environmental impact of the assessed element) is not applicable for this issue as the insulation is assessed as a single material in BREEAM issue Mat 04 and not as part of a larger building element containing other materials (as in BREEAM issue Mat 01).
Criteria | Interim design stage |
Final post construction stage
|
---|---|---|
All |
One or more of the appropriate evidence types listed in The BREEAM evidential requirements section can be used to demonstrate compliance with these criteria. |
|
All |
A completed copy of the Mat 04 Calculator tool |
As per interim design stage |
None.
BREEAM UK New Construction non-domestic buildings technical manual 2014
Reference: SD5076 – Issue: 5.0
Date: 23/08/2016
Copyright © 2016 BRE Global. All rights reserved.