Number of credits available | Minimum standards |
---|---|
4 |
Yes |
To encourage a properly planned handover and commissioning process that reflects the needs of the building occupants.
This issue is split into four parts:
The following is required to demonstrate compliance:
None.
Ref |
Terms |
Description |
---|---|---|
Shell and core | ||
CN1 |
Applicable assessment criteria |
Commissioning and testing schedule and responsibilities, commissioning building services, criteria 1 to 6 Option 1 - Shell only: These criteria are not applicable. Testing and inspecting building fabric Option 1 - Shell only: criteria 8 and 9
Handover, criteria 10 to 11 Option 1 - Shell only: These criteria are not applicable. Option 2 - Shell and core: Criterion 10 only is applicable. The guide includes, as far as possible, all relevant sections regarding the services and fabric installed. On completion of works the building owner/agent/user hands it over to the fit-out contractor, who can then complete the relevant sections based on the fit-out strategy. Handover, criterion 11 Both options: This criterion is not applicable. Refer to Appendix D – BREEAM UK New Construction and Shell and Core Project Assessments for a more detailed description of the above shell and core assessment options. |
Simple buildings | ||
CN2 |
Applicable assessment criteria |
Commissioning and testing schedule and responsibilities (1 credit)
Handover (1 credit)
|
General | ||
CN3 |
Other appropriate standards See criterion 2. |
Appropriate standards for completion of this criterion are referenced accordingly and include standards covering: Building fabric
Commercial refrigeration
Fume cupboards
Microbiological safety cabinets
|
CN3.1 |
Process-related equipment |
Any process or manufacture-related equipment specified as part of the project may be excluded from the assessment of the commissioning credits, except where they form an integral part of the building HVAC services, such as some heat recovery systems. |
BMS commissioning procedures |
Where a building management system (BMS) is specified, the following commissioning procedures must be carried out:
|
|
Scope of the thermographic survey | The thermographic survey must cover 100% of the treated spaces, unless it is a large complex building (see CN3.4), and ensure that all elements of the building fabric that enclose an internal heated and/or conditioned (treated) zone of the building will be tested. This includes internal walls separating treated and untreated zones. | |
Thermographic survey of large complex buildings | In the case of large and complex buildings, it may be impractical for the thermographic survey and air-tightness testing to cover 100% of the building. Where a complete thermographic survey is deemed impractical by a Level 2 qualified thermographic surveyor, the guidance in air tightness standard TSL23Measuring air permeability of building envelopes (non-dwellings), Technical standard Level 2 (TSL2). The Air Tightness Testing and Measurement Association (ATTMA). October 2010. should be followed on the extent of the survey and testing. This could include airports, large hospitals and high-rise buildings. |
|
CN3.5 |
Remediation work | Any remediation work undertaken, resulting from a thermographic survey and air-tightness test of the building, should be robust and durable, i.e. the remedial work must have the same performance characteristics and life expectancy of the surrounding element(s). |
CN3.6 |
Thermographer qualification | The thermographic survey is normally undertaken by a Suitably Qualified Professional holding a valid Level 2 certificate in thermography (see Relevant definitions). Where a Level 2 thermographer is not available at the site, the survey may be undertaken by a Level 1 thermographer and then the images interpreted by a Level 2 thermographer. |
Alternatives to Thermographic Survey |
A thermographic survey is considered the primary means through which the testing inspection of building fabric criteria could be met. However there may be other robust means of testing that also fulfill the aim of the credit. Assessors should consider how such methodology addresses all of the elements of the criteria (e.g. insulation, thermal bridging, air leakage and the general integrity of the building fabric) as well as what is appropriate for the building type and construction. Assessors should then contact BRE Global for approval before submitting their final assessment report. |
None.
Criteria | Interim design stage |
Final post construction stage
|
---|---|---|
All |
One or more of the appropriate evidence types listed in The BREEAM evidential requirements section can be used to demonstrate compliance with these criteria. |
|
9, 10 | Refer to generic evidence requirement above | Thermographic survey and Level 2 thermography certificate |
10, 11 | Refer to generic evidence requirement above |
Building User Guide |
BREEAM UK New Construction non-domestic buildings technical manual 2014
Reference: SD5076 – Issue: 5.0
Date: 23/08/2016
Copyright © 2016 BRE Global. All rights reserved.